Calculating Production Delivery Date using “Agile” methodology — A flavor of story/feature/sub-feature mapping

Estimating projects/initiatives is not easy if you don’t have a right approach. You can be in MS Project land trying to figure out little details, but those details change and then you are stuck maintaining schedules in MS Project. You spend a lot of time tweaking the tool instead of proper planning.
A lot of companies are trying to change to use the “Agile” methodology and I am putting the word “Agile” in quotes because there is no company out there that is following exactly what you are taught in ScrumMaster courses and SAFe courses. That means that companies sooner or later end up doing what works for them and that could be an approach that belongs somewhere on the line between Waterfall and Agile; for some companies closer to Agile, and for some companies closer to Waterfall.
For example a lot of companies get a list of projects/initiatives that need to be estimated at high-levelprioritized and approved by a board before projects can be worked on. Then when they are estimated and approved, you are asked to provide project schedules with milestones and deadlines with very high-level requirements. Then some of these organizations say “let’s run these projects using the agile methodology”. What does that really mean?
What does this really mean to the delivery teams if somebody already provided the high-level estimates and basically to some degree committed when the project will be delivered?
You can still stay positive about it and concentrate on understanding the requirements and properly breaking down the project/initiative into manageable pieces and ultimately calculating the true production delivery date that you can go back to the business team with.
Let me explain how I approach this. What works for me is reading the requirements document or epics and user stories and breaking down the project into a list of features and sub-features. Then if the requirements document is written in such a way that it lists the user stories, you can easily distribute these user stories into the appropriate sub-features. If the requirements document does not explicitly list the user stories, then I would put a product owner hat on and extrapolate the user stories out of the requirements document embedded in different paragraphs.
Now that I have all the user stories under each sub-feature, I can do some high-level estimating on each story and the unit for estimation is the number of days. It is not some virtual story points and it is not the hours; it is the number of days (8h=1day).
After estimating each user story under each sub-feature, you can add up the estimates and have the list of sub-features and numbers for each sub-feature.
Now that you have the list of sub-features and estimate for each sub-feature, it is all fun after this point. It is fun because I like using Trello website to perform this mapping or pre-plan all the sprints and ultimately produce the deadline (production delivery date), because that’s what business expects from us. NOTE: In this exercise, I don’t do sprint planning at the user story level; I do this exercise of sprint pre-planning (mapping) at the sub-feature level in order to produce that deadline and to have a rough idea how each sub-feature needs to be worked on throughout the project.
What are the steps to be taken before playing the drag-and-drop game in Trello?
  • Decide on the duration of the sprint (let’s say 4 weeks). I understand that the 4-week sprint is on the longer side, but this is just an example.
  • Take the list of sub-features and estimates and break down each sub-feature into multiple sub-feature parts that are each 5 days worth of work. For example, if you have a sub-feature that has the estimate of 20 days, then you would break that sub-feature into Sub-Feature A part 1, Sub-Feature A part 2, Sub-Feature A part 3, and Sub-Feature part 4.
  • Now you are ready to plug this all into Trello backlog list and then the game of dragging and dropping starts :)
Here is how it could look like in the backlog list when you start:
Now that you have all the sub-feature parts in the backlog, it is time to gauge what the optimal number of resources is. Let’s do some simple math.
  • 6 resources
  • 4 week sprints (20 working days)
  • if everybody is a robot, then the team should be able to chunk away 120 days (6x20) out of the estimates. Yeah right !!! With all the meetings and interactions between teammates, a reasonable number to achieve in each sprint would be 60–80 days worth of work. If each part of the given sub-feature is equivalent to 5 days worth of work from the estimates, then you should be able to drag and drop 10+ of those parts into a given user sprint.
You as the technical lead and technical project manager know best how each sub-feature is related to each other and you are deciding those things as you are loading each sprint with the list of sub-feature parts.
Here is how it may look after going through this exercise. It looks like the duration of the project would be around 14 weeks (3.5 months). If you know what the start date is, then you can easily calculate the production launch date. You also know when you need to start each sub-feature and when each sub-feature is supposed to be completed. That can help you point out some major milestones to your senior management team.
You are done. Provide your boss the duration of the project, major milestones and the production launch date that you can achieve based on these high-level estimates.
What’s next?
Well, now you need to share this with the delivery team and help out the team do proper sprint planning at the user story level by using this sub-feature plan. I happened to use Trello just for the purposes of “sub-feature” planning, but when it comes to sprint planning at the user-story level, your team will need to use whatever tool your company approved.
Good luck and have fun.
Thank you for reading this article. Please follow me here or check out my personal blog: http://www.almirsCorner.com
Almir Mustafic


Comments

Popular posts from this blog

Brand New programming language and one solution OR …

Brand New programming language and one solution OR Two existing programming languages, one solution for EACH? I understand that there is no right or wrong. It all depends on your software architecture, team structure, team skills and other factors, but I still want to explain the scenario as it may look familiar to some. Let me explain. Let’s assume that you have microservices and common libraries in two major programming languages. You have some teams who are experts in one and some teams experts in the other programming language. Now you need to come up with a solution for a scenario that all teams will need to leverage. Let’s assume that your cloud platform has an off-the-shelf approach for this but it is supported by a 3rd programming language that your teams do not have much experience in. What is the right thing for your organization and not just from the technical point of view? A) Do you embrace what your cloud platform gives you off the shelf and implement thi...

10,000 foot level view in technology

10,000 foot level view in technology: How useful is it? What can be done at this level? If the 30,000 foot level is the CTO level, then consider the 10,000 foot level as the level that software engineering managers and directors operate at. To achieve the success at 10,000 foot level, you as a software engineering manager need to dive deep into technical details, help the team lay the foundation from BOTH organizational and technical side. It is the little moves that get the team to this level. Once the team’s applications and results at that level, then you as a manager have ability to perform the high level analysis and troubleshooting without necessarily being in code on daily or weekly basis. Therefore, your ability to troubleshoot technical issues at the 10,000 foot level is a testament to the great work of your team. Go TEAM !! Almir Mustafic

Programming languages to teach students in high-school and university

Python-like or C-like as the language to introduce programming to students in high school and university? The question is: Do you introduce programming concepts to high-school/university students using languages that handle memory and other things for you or do you start introducing all of these concepts in languages like C that require you to understand all aspects. I will tell you what worked for me. I was introduced to programming in grade 10 using Basic programming language. There was a version called Better Basic and also Quick Basic. Then in grade 11 we learned procedural programming in a programming language called Turing (not Turing machine but a Pascal-like language developed by University of Toronto for teaching purposes). Then a year later, I started getting interested in C and C++. As you can see, I eased into the languages that introduced me to NULL exceptions and memory leaks :) With this approach I was not overwhelmed and this set up the foundation for a fun journey ...